Small residential · Co. Wicklow
Ballycrone, Kilcoole, Co Wicklow
Granted 18 Aug 2023
Key facts
- Planning application 221231 at Ballycrone, Kilcoole, Co Wicklow: 2 homes.
- It was received by Wicklow County Council on 21 Nov 2022.
- Status: Granted 18 Aug 2023.
Source: the Wicklow County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Kilcoole · Planning applications in Co. Wicklow
Since you last looked
Worked out in this browser from the record's own dates. We do not send emails about it.
Council register
The council's register shows: Granted on 18 Aug 2023.
Search the Wicklow planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
2 homes
proposed two dwellings with connections to services, entrance to public road to serve both dwellings and associated works
- Location
- Kilcoole, Co. Wicklow Map
- Council
- Wicklow County Council
- Planning reference
- 221231
Numbers and dates
- Homes
- 2
- Floor area
- 258 m²
- Project type
- Small residential
- Received
- 21 Nov 2022
- Granted
- 18 Aug 2023
- Site start
- 11 Apr 2024
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 221231 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Wicklow County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 11 Apr 2024Work started · Two dwellings with connections to services and a combined entrance to the public road
- Completion certificate recordedRecorded in Apr 2024 · 2 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 4 Oct 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.