Planning

Permission to Build: about one in three larger housing developments notifies a site start within a year

How many housing developments of 20 or more homes granted in Meath, Kildare, Louth and Wicklow since November 2024 have notified a site start, and how soon.

Chart

Bar chart: housing developments granted per half-year from November 2024 to October 2026 in Meath, Kildare, Louth and Wicklow, and how many have notified a site start: 4 of 8, 14 of 27, 13 of 31, 12 of 28 and 1 of 19
Final decisions to grant by half-year, and how many have notified a site start by 9 Nov 2026. PlanningBrief

Key figures

113 granted, 44 with a site start notified

Between 15 Nov 2024 and 22 Oct 2026, 113 housing developments of 20 or more homes in Meath, Kildare, Louth and Wicklow received a final decision to grant permission. By 9 Nov 2026, 44 of them had notified a site start.

A permission normally lasts five years, and a recent decision has had little time to start, so the figures below compare developments by how long ago they were granted.

  • 113housing developments of 20+ homes with a final decision to grant, 15 Nov 2024 to 22 Oct 2026
  • 44of them with a site start notified by 9 Nov 2026
  • 22 of 61granted at least a year ago notified a site start within 12 months
  • 14 of 81granted at least six months ago notified a site start within six months

Timing

About half of the permissions granted by mid-2025 have a site start

Of the 35 developments granted by the end of June 2025, 18 have notified a site start. Of the 61 developments granted by early November 2025, 29 have now notified a site start, 22 of them within a year of the decision. Of the 19 granted from July to 22 October 2026, one has so far.

By county, 12 of 26 developments in Kildare have notified a site start, 12 of 33 in Louth, 13 of 31 in Meath and 7 of 23 in Wicklow. The numbers in each county are small, so we do not compare them as rates.

Final decisions to grant by half-year, and how many have notified a site start

  • Decided to grant
  • Site start notified

Nov and Dec 2024

Jan to Jun 2025

Jul to Dec 2025

Jan to Jun 2026

Jul to 22 Oct 2026

Housing developments of 20 or more homes in Meath, Kildare, Louth and Wicklow. Site starts to 9 Nov 2026. Source: PlanningBrief records of planning decisions and site starts.
Show the figures as a table
DevelopmentsDecided to grantSite start notified
Nov and Dec 202484
Jan to Jun 20252714
Jul to Dec 20253113
Jan to Jun 20262812
Jul to 22 Oct 2026191

Left out

Appeals and refusals

We left out developments still under appeal to An Coimisiún Pleanála (19), refused on appeal (4) or still inside the four-week appeal period (5). Where the Commission granted permission on appeal, we count the time from its decision.

How we counted

Method

We grouped planning applications into developments, so that an amendment or an extension of time is not counted as a new development, and kept those of 20 or more homes. We count developments, not homes. A development counts as started when a site start was notified for that permission after its decision. Two of the 44 developments notified a site start with a start date later in November 2026. For 24 of the 113 the council's final grant date is not yet in our records, so we say decided to grant. We checked a random sample of 50 developments against the councils' own planning files. One of the 30 with no site start in our records had one listed there, so the counts here may be slightly low. All 16 site starts already listed on a council file were on the right permission. No site start in our records does not mean no work has taken place.

The record

  1. Site starts

What changed: First edition of Permission to Build: final decisions to grant from 15 Nov 2024 to 22 Oct 2026, site starts to 9 Nov 2026.

References

Sources

We link to the council's own file so you can check the official record before you act.