Key figures
113 granted, 44 with a site start notified
Between 15 Nov 2024 and 22 Oct 2026, 113 housing developments of 20 or more homes in Meath, Kildare, Louth and Wicklow received a final decision to grant permission. By 9 Nov 2026, 44 of them had notified a site start.
A permission normally lasts five years, and a recent decision has had little time to start, so the figures below compare developments by how long ago they were granted.
- 113housing developments of 20+ homes with a final decision to grant, 15 Nov 2024 to 22 Oct 2026
- 44of them with a site start notified by 9 Nov 2026
- 22 of 61granted at least a year ago notified a site start within 12 months
- 14 of 81granted at least six months ago notified a site start within six months
Timing
About half of the permissions granted by mid-2025 have a site start
Of the 35 developments granted by the end of June 2025, 18 have notified a site start. Of the 61 developments granted by early November 2025, 29 have now notified a site start, 22 of them within a year of the decision. Of the 19 granted from July to 22 October 2026, one has so far.
By county, 12 of 26 developments in Kildare have notified a site start, 12 of 33 in Louth, 13 of 31 in Meath and 7 of 23 in Wicklow. The numbers in each county are small, so we do not compare them as rates.
Left out
Appeals and refusals
We left out developments still under appeal to An Coimisiún Pleanála (19), refused on appeal (4) or still inside the four-week appeal period (5). Where the Commission granted permission on appeal, we count the time from its decision.
How we counted
Method
We grouped planning applications into developments, so that an amendment or an extension of time is not counted as a new development, and kept those of 20 or more homes. We count developments, not homes. A development counts as started when a site start was notified for that permission after its decision. Two of the 44 developments notified a site start with a start date later in November 2026. For 24 of the 113 the council's final grant date is not yet in our records, so we say decided to grant. We checked a random sample of 50 developments against the councils' own planning files. One of the 30 with no site start in our records had one listed there, so the counts here may be slightly low. All 16 site starts already listed on a council file were on the right permission. No site start in our records does not mean no work has taken place.
The record
What changed: First edition of Permission to Build: final decisions to grant from 15 Nov 2024 to 22 Oct 2026, site starts to 9 Nov 2026.