Planning lead

Current planning presentation

Retention permission is sought for: Part (104 sq.m gross) of the first floor currently in light industrial use at Unit 5-9: Enlargement of ground floor window at Unit 5-9 on the north elevation enlargement of first floor windows at Unit 5-9 on the south elevation. Planning permission is sought for: (i)The change of use of Unit 4 (of 292.5 sq.m), including that part at first floor (104 sq.m) for which retention permission is sought, from light industrial use to office based industry use and amalgamation of Unit 4 with Unit 5-9 (1,505 sq.m gross) to provide a single office based industry unit of 1,797.5 sq.m gross together with all associated and ancillary works, including internal fit-out. (ii) At the south elevation of Unit 4: a. At ground floor, existing door, external shutter box, all supports and electrics to be removed and to be replaced with a new glazed door unit, and existing roller shutter door and all supports/electrics to be removed and replaced with new window unit. b. At first floor, 2 no. new aluminium/glass windows. (iii) 4 no. bicycle parking spaces, including provision for cargo bike.

Planning authority
South Dublin County Council
Lead planning reference
SD25A 0125W
Application date
19 Aug 2025
Decision date
29 Aug 2025
Project type
Commercial fit-out

Planning

Planning records

SD25A 0125W · Planning application

South Dublin County Council · Granted 29 Aug 2025

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

Commencement notice · 2025-11-21

Change of use at Unit 4, Turnpike Business Centre, Dublin 22. This refurbishment (c.302.6m2) shall include change of use at Unit 4 (warehouse/industrial to offices) and minor material alterations to accommodate small office alteration and demolition of compartment wall between units 4 and unit 5 at Turnpike Business Centre, Turnpike Lane, Ballymount, Dublin 22.

1810 m² · Stated on the commencement notice

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

Completion certificate

2025-11 · Scope not stated