Connected projectGranted

309 dwellings, principally located in Bennetstown (townland) to the west of the...

Granted · principally located in Bennetstown (townland) to the west of the R157 and also extending into Pace & Dunboyne (townlands), Dunboyne North, Co. Meath

Planning units309Stated in the planning application
Planning floor area35380 m²Stated in the planning application
Planning records1
Commencement events6
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

a Large-Scale Residential Development: permission for the following Large-Scale Residential Development consisting of: i) 309 no. residential units comprising 169 no. dwelling houses and 140 no. apartments/duplexes providing a mix of 1, 2, 3 and 4-bed units. The dwelling houses range in height from 2-3 storeys. The apartments/duplexes are in 8 no. blocks (i.e. Blocks A-H) ranging in height from 3 to 4 storeys; ii) a 2 storey creche; iii) modifications to the R157 regional road including changes to the existing carriageway/traffic lanes, the replacement of an existing roundabout with a new signalised junction and the provision of a northern arm off the new signalised junction; iii) a new signalised junction and link road (including new bridge over the River Tolka) connecting the R157 and the Old Navan Road; iv) the provision of footpaths, cycle lanes and 2 no. pedestrian crossings on the existing M3 Parkway access road, v) a foul pumping station and connection to the existing public sewerage system via the Old Navan Road; vi) a watermain connection to the north of the site at Pace (townland); vii) 3 no. ESB substation/kiosks; viii) temporary raised levels and soil storage to the south west of the site; ix) reprofiling of lands, construction of conveyance swales and a surface water runoff retention area as part of pluvial flood mitigation measures and x) all associated ancillary development works including footpaths, cycle lanes, car and bicycle parking, drainage, public lighting, bin storage, boundary treatments and landscaping/amenity areas at this site principally located in Bennetstown (townland) to the west of the R157, and also extending into Pace & Dunboyne (townlands), Dunboyne North, Co. Meath. Access will be via 2 no. new signalised junctions on to the R157 comprising 1 no. new vehicular access point to the southeast along the R157 and via 1 no. new vehicular access point to the north along a new northern arm off a new signalised junction which will replace the existing roundabout on the R157. The planning application red line boundary overlaps with planning ref. 23/60290, 23/60065 and 23/424. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) has been submitted to the planning authority with the application

Planning authority
Meath County Council
Lead planning reference
24/60805
Application date
30 Sep 2024
Decision date
15 Nov 2024
Project type
Large residential

Planning

Planning records

24/60805 · Planning application

Meath County Council · Granted 15 Nov 2024

309 units · Stated in the planning application

35380 m² · Stated in the planning application

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

Commencement notice (owner-supplied) · 2026-01-02

Commencement evidence is linked; rejected quantities remain only in the sealed source artifact.

140 units · Stated on the commencement notice
1658 m² · Stated on the commencement notice

Commencement notice · 2026-01-02

Construction of 169 dwellings ranging from 2-3 storey, to gether with associated site works.

169 units · Stated on the commencement notice
15206 m² · Stated on the commencement notice

Commencement notice (owner-supplied) · 2026-02-03

Construction of 1 no. ESB substation which includes a switch room together with site associated works located at Bennetstown, Dunboyne, Co. Meath

21 m² · Stated on the commencement notice

Commencement notice (owner-supplied) · 2026-02-23

Commencement evidence is linked; rejected quantities remain only in the sealed source artifact.

140 units · Stated on the commencement notice
1494 m² · Stated on the commencement notice

Commencement notice (owner-supplied) · 2026-02-23

Commencement evidence is linked; rejected quantities remain only in the sealed source artifact.

140 units · Stated on the commencement notice
1288 m² · Stated on the commencement notice

Commencement notice (owner-supplied) · 2026-06-03

Construction of a 3 & 4 storey residential block comprising of 8 no. apartments and 6 no maisonettes

14 units · Stated on the commencement notice
1288 m² · Stated on the commencement notice

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.