~1 dwelling, 12, Fortfield Grove, Terenure, Dublin 6W
Granted · 12, Fortfield Grove, Terenure, Dublin 6W
Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.
Planning lead
Current planning presentation
The development will consist of front elevation amendments by the addition of a new bay window at ground floor(existing garage) and 1st floor (bedroom 4) in conjunction with front entranced door adjustment for energy improvement and existing pitched roof and hipped end extended to cover existing flat roof area; the conversion of the existing garage at ground floor level to a new study/home office; two storey extension to the rear and side elevation to incorporated extended utility room and first floor en-suite bathroom.
- Planning authority
- South Dublin County Council
- Lead planning reference
- SD24B/0003
- Application date
- 4 Mar 2024
- Decision date
- 27 Mar 2024
- Project type
- House extension
Planning
Planning records
SD24B/0003 · Planning application
South Dublin County Council · Granted 27 Mar 2024
14.2 m² · Stated in the planning application
Open official recordPlanning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.
Building control evidence
Separate commencement events
Commencement notice (owner-supplied) · 2025-09-02
The development will consist of front elevation amendments by the addition of a new bay window at ground floor(existing garage) and 1st floor (bedroom 4) in conjunction with front entranced door adjustment for energy improvement and existing pitched roof and hipped end extended to cover existing flat roof area; the conversion of the existing garage at ground floor level to a new study/home office; two storey extension to the rear and side elevation to incorporated extended utility room and first floor en-suite bathroom.
177 m² · Stated on the commencement notice
Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.
Appeal evidence
Appeals
No appeal event is linked.
Completion evidence
Completion records
No completion evidence is linked.