Connected projectGranted

Temporary/event, Smithstown, Shannon, Co. Clare V14VY67

Granted · Smithstown, Shannon, Co. Clare V14VY67

Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

for 1) Construction of a new 540 m2 fully bunded sodium hypochlorite building with a 60 m2 lower mezzanine floor and 10 m2 upper mezzanine floor, including 2No. external underground brine storage tanks; 2) Construction of a new 102 m2 mezzanine floor extension to an existing storage area within an existing warehouse; 3) Construction of a new 32 m2 extension to an existing ESB substation on site; 4) Demolition of an existing internal ramped accessway and removal of 2 No. existing temporary containers off site; 5) All ancillary site development works and services to facilitate the development including drainage, external plant, external pipework to adjacent storage tank and utility connections. The proposed development site is controlled by an Industrial Emissions Licence (Register No. P0076-02) authorised by the Environmental Protection Agency.

Planning authority
Clare County Council
Lead planning reference
2560489
Application date
6 Aug 2025
Decision date
29 Sep 2025
Project type
Temporary/event
Public promoter
Chemifloc Limited
Public agent
Pemcas Ltd

Planning

Planning records

2560489 · Planning application

Clare County Council · Granted 29 Sep 2025

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

Commencement notice (owner-supplied) · 2026-03-23

Construction of a new 29.7 m2 extension to an existing ESB substation on site and all ancillary site development works.

30 m² · Stated on the commencement notice

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.