Appeal/FI, Island Upper, Rossminoge
Granted · Island Upper, Rossminoge
Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.
Planning lead
Current planning presentation
Permission to construct a new agricultural yard to include stables
- Planning authority
- wexfordcountycouncil
- Lead planning reference
- 20241620
- Application date
- 20 Dec 2024
- Decision date
- 6 Jun 2025
- Project type
- Appeal/FI
Exact evidence
Planning records
322919 · Planning record
An Coimisiún Pleanála
Open official record20241620 · Planning application
Wexford County Council · Refused · 2025-06-06
Open official recordPlanning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.
Building control evidence
Separate commencement events
CN0142292WX · 2026-05-18
Construction of an Agricultural Stable and associated works in Island Upper, Rossminoge, Craanford
1389 m² · Source-stated event-specific quantity
Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.
Appeal evidence
Appeals
322919 · Appeal record
Grant Permissions with Conditions · 2025-10-30
Open official appeal caseCompletion evidence
Completion records
No completion evidence is linked.