Save to pipeline
Connected projectGranted

1 dwelling, BALLYARR GLEBE, RAMELTON, LETTERKENNY PO

Granted · BALLYARR GLEBE, RAMELTON, LETTERKENNY PO

Planning units1Source-stated
Planning floor area286 m²Source-stated; verify
Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

ERECTION OF A DWELLING HOUSE WITH SEPTIC TANK AND DOMESTIC GARAGE INCLUDING ALL ASSOCIATED SITE DEVELOPMENT WORKS

Planning authority
donegalcountycouncil
Lead planning reference
2561465
Application date
26 Aug 2025
Decision date
11 Dec 2025
Project type
One-off house

Exact evidence

Planning records

2561465 · Planning application

Donegal County Council · CONDITIONAL · 2025-12-11

1 units · Source-stated planning-record quantity

286 m² · Source-stated planning-record quantity

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

2026-05-21

Construction of a dwelling house at Ballyarr Glebe with all associated site development works.

1 units · Source-stated event-specific quantity
241 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.