Planning lead

Current planning presentation

the construction of single storey extensions to the front and side of the existing clubhouse building comprising a community room, additional sanitary facilities, referees room, coffee kiosk, internal alterations to existing building, extension of entrance canopy and a connection to the public sewer, together with all associated site works.

Planning authority
waterfordcityandcountycouncil
Lead planning reference
2560122
Application date
28 Feb 2025
Decision date
17 Apr 2025
Project type
Planning record

Exact evidence

Planning records

2560122 · Planning application

Waterford City and County Council · CONDITIONAL · 2025-04-17

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

2026-03-03

Extension to clubhouse building and associated site works

101 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.