Connected projectGranted

Demolition, Kildare Innovation Centre, Barnhall Road, Leixlip

Granted · Kildare Innovation Centre, Barnhall Road, Leixlip

Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

for the demolition of an existing 23m2 single storey entrance porch at Building No.3 (North-East elevation) and removal of entrance pathway. Construction of new 148m2 single storey reception building at point of existing entrance on North-East façade to include a sheltered canopy public entrance with separate staff entrance, reception waiting area, tea station, 1 no. office room, 1 no. meeting room and a wheelchair accessible W.C. all with associated ancillary, drainage and landscape works including permeable paving serving as attenuation tank and soakaway

Planning authority
Kildare County Council
Lead planning reference
25/60200
Application date
28 Feb 2025
Decision date
27 Jun 2025
Project type
Demolition

Planning

Planning records

25/60200 · Planning application

Kildare County Council · Granted 27 Jun 2025

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

Seven-day notice · 2025-09-30

Demolition of an existing 23m2 single storey entrance porch at Building No.3 (North-East elevation) and removal of entrance pathway. Construction of new 148m2 single storey reception building at point of existing entrance on North-East façade to include a sheltered canopy public entrance with separate staff entrance, reception waiting area, tea station, 1 no. office room, 1 no. meeting room and a wheelchair accessible W.C. all with associated ancillary, drainage and landscape works including permeable paving serving as attenuation tank and soakaway

145 m² · Stated on the commencement notice

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.