Infrastructure, 3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin...

Granted · 3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22

Planning floor area47714.5 m²Source-stated; verify
Planning records1
Commencement events5
Appeals0
Completion evidence8

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

Provision of 4 new information and communications technology (ICT) Facility buildings and associated development at the subject site, superseding elements of the extant planning permissions on site (Reg. Ref.: SD18A/0068 and Reg, Ref.: SD19A/0185). The application site is subject to an EPA Industrial Emissions Licence (Ref. No, : P1113-01) relating to the Energy Centre permitted on site, The single storey Energy Centre, gas pressure reduction station, and 110kV Gas Insulated Switchgear (GIS) substation permitted under Reg, Ref.: SD18AI0068 and Reg. Ref.: SD19AI0185 will be constructed as previously approved and are not affected by the current application. The proposed development will comprise the following: The construction of 4 ICT Facility buildings (ICT Facilities 1, 2, 3, and 4) with a combined total gross floor area {GFA) of c. 47,564.5 sq.m, Each ICT Facility building includes associated external plant areas, totalling c, 20,649.5 sq, m, ICT Facilities 1, 2, and 3 will be located in the eastern portion of the site, and each comprise a GFA of c. 15,196 sq.m (including ancillary office and administration space) over part two and part three levels with a maximum height of c, 25 metres and a parapet height of c, 19.5 metres, Each of the ICT Facilities will include an associated external plant area of c, 6,624 sq, m, ICT Facility 4 will be located in the southern portion of the site and comprises a GFA of c, 1,976.5 sq, m (including ancillary office and administration space) over two levels with a maximum height of c, 15 metres and a parapet height of c. 10.5 metres, This ICT Facility includes an associated external plant area of c. 777.5sq.m, Each ICT Facility building will accommodate ICT equipment halls, associated electrical and mechanical plant rooms, loading bays, maintenance and storage space, office administration areas, and screened plant. Construction of internal road network and circulation areas, footpaths, provision of 153 no. car parking spaces and 54 no, cycle parking spaces. Connections to vehicular access routes, roads, services and permitted infrastructure relating to the Energy Centre and 110kV GIS substation permitted under Reg, Ref.: SD18A/0068 and Reg, Ref.: SD19A/0185. Provision of emergency generators with associated flues, water storage tanks and associated pump rooms (comprising 150 sq, m in total) to serve each of the proposed ICT Facility Buildings. Hard and soft landscaping and planting, lighting, and all associated works, including underground foul and storm water drainage network, boundary treatments and security fencing, attenuation areas, and utility cables.

Planning authority
southdublincountycouncil
Lead planning reference
SD20A/0309
Application date
24 Feb 2021
Decision date
23 Mar 2021
Project type
Infrastructure
Value band
€30m+

Exact evidence

Planning records

SD20A/0309 · Planning application

South Dublin County Council · GRANT PERMISSION · 2021-03-23

47714.5 m² · Source-stated planning-record quantity

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

2022-07-08

It is proposed to construct a new digital data facility centre in Clondalkin. Dub 10, Building 12 will consist of 3 storeys (ground, level 1 and level 2), with a mezzanine level between ground and level 1.The building will mainly contain computer and electrical switching equipment and will have a low occupancy consisting of technicians maintaining and supervising equipment.

4310 m² · Source-stated event-specific quantity

2023-12-05

Construction of a new information and communications technology (ICT) Facility building and associated development at 3-4, Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22. The proposed development will comprise the construction Building DUB11, (Formerly ICT 1) through 2 phases. Phase 1 works comprise of the external envelope and structure only and will not be for occupation. Phase 2 will comprise of the internal work and will be finalised prior to occupation.

17112 m² · Source-stated event-specific quantity

2024-07-04

Construction of a new information and communications technology (ICT) Facility building and associated development at 3-4 Crag Avenue, Clondalkin Industrial Estate, Clondalkin, Dublin 22. The proposed development will comprise the construction of Building DUB11, (Formerly ICT 1). This notice is for Phase 2 which comprises the internal (CSA) fit out and M&E works. This phase will be for occupation.

15196 m² · Source-stated event-specific quantity

2025-05-21

It is proposed to provide an ancillary building on the Echelon DUB 10 site. The building is a pump house building for the site.

107 m² · Source-stated event-specific quantity

2025-05-21

It is proposed to provide an ancillary building on the Echelon DUB 10 site. The building is a pump house building for the site.

50 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

Completion certificate

2022-07 · Scope not stated

Completion certificate

2023-12 · Scope not stated

Completion certificate

2024-07 · Partial completion

Completion certificate

2024-07 · Partial completion

Completion certificate

2024-07 · Partial completion

Completion certificate

2024-07 · Partial completion

Completion certificate

2025-05 · Scope not stated

Completion certificate

2025-05 · Scope not stated