Infrastructure, Tonery's Pub, 144 Bohermore, Galway
Granted · Tonery's Pub, 144 Bohermore, Galway
Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.
Planning lead
Current planning presentation
Permission for development which consists of 1. The demolition of the existing Public House and adjoining shed/garage structures; 2. The construction of a hotel development with 3 floors over ground floor level and 2 floors below ground floor level comprising of 182 no. rooms. The proposed development contains reception areas, dining and resident lounge spaces, kitchen, storage, staff welfare areas, plant room, enclosed service area, ESB substation and switch room, refuse and bicycle storage areas; 3. All other associated site works, including public realm improvements, water/wastewater services, landscaping and pedestrian linkages, roof mounted solar panels, lighting and ancillary signage.
- Planning authority
- galwaycitycouncil
- Lead planning reference
- 2360064
- Application date
- 14 Sep 2023
- Decision date
- 11 Apr 2024
- Project type
- Infrastructure
Exact evidence
Planning records
2360064 · Planning application
Galway City Council · CONDITIONAL · 2024-04-11
Open official recordPlanning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.
Building control evidence
Separate commencement events
SN0013912GY · 2026-03-23
The construction of a hotel development with 3 floors over ground floor level and 2 floors below ground floor level at Bohermore, Co. Galway
6143 m² · Source-stated event-specific quantity
Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.
Appeal evidence
Appeals
No appeal event is linked.
Completion evidence
Completion records
No completion evidence is linked.