Save this project to account
Connected projectGranted

Public / civic, Saint Mary's Primary School, Grace Park Road Loughanaskin...

Granted · Saint Mary's Primary School, Grace Park Road Loughanaskin, Athlone Co. Westmeath

Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

a standalone two-storey classroom building (Gross Floor area 2,093 sq. m) comprising of eleven additional mainstream classrooms, a dedicated Special Educational Needs (SEN) unit with two safe-base classrooms and a multi-sensory room, a new school office, nine special education tuition rooms, one home school liaison, staff facilities, and associated ancillary accommodation The development will also include a new vehicle and pedestrian entrance from John Paul Park, road and junction upgrades on John Paul Park, and relocation and reconfiguration of parking spaces along John Paul Park. Within St Mary's Primary school curtilage, a fire tender access to the new building, new boundary treatments along the site frontage, and all associated site development and landscaping works above and below ground

Planning authority
westmeathcountycouncil
Lead planning reference
2560366
Application date
22 Jul 2025
Decision date
15 Sep 2025
Project type
Public / civic
Value band
€1m–3m
Public agent
Van Dijk Architects Ltd.

Exact evidence

Planning records

25/60366 · Planning application

Westmeath County Council · CONDITIONAL · 2025-09-15

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

SN0013562WH · 2026-01-05

A standalone two-storey classroom building comprising eleven additional mainstream classrooms, a dedicated Special Educational Needs (SEN) unit with two safe-base classrooms and a multi-sensory room, a new school office, nine special education tuition rooms, staff facilities, and associated ancillary accommodation.

2012 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.