Save this project to account
Connected planning records

Planning case 19871

Wicklow County Council · 19871 · Enniskerry, Wicklow

Latest linked evidence

Notified commencement · 2024-03-25

CN0113150WW · Phase 3 and Part of Phase 4 of 4; Construction of 9 No. Detached Dwellings as completion of Development of 27 No. Detached Dwellings

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    19871

  2. Planning decision

    19871

    Conditional permission

  3. Grant date recorded

    19871

  4. Notified commencement

    CN0085576WW

    Phase 1 of 4; Construction of 6 No. Detached Dwellings as part of development of 27 no. Detached Dwellings

    6 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    CN0096044WW

    Part of Phase 2 of 4: Construction of 2 No. Detached Dwellings as part of Development of 27 No. Detached dwellings

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    CN0100985WW

    Part of Phase 2 of 4; Construction of 8 No. Detached Dwellings as part of Development of 27 No. Detached Dwellings

    10 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    CN0108216WW

    Part of Phase 4 of 4: Construction of 2 No. Detached Houses as part of Development of 27 No. Detached Dwellings

    2 units stated for this notice or phase; not a project total.

    · Notice evidence

  8. Notified commencement

    CN0113150WW

    Phase 3 and Part of Phase 4 of 4; Construction of 9 No. Detached Dwellings as completion of Development of 27 No. Detached Dwellings

    9 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.