Connected planning records

Planning case LRD23A0001

South Dublin County Council · LRD23A0001 · Dublin, Dublin

Latest linked evidence

Notified commencement · 2024-03-12

Construction of ESB Substation and associated site works located on Citywest Avenue, Brownsbarn, South Dublin.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    LRD23A0001

    Official source

  2. Planning decision

    LRD23A0001

    Permission granted

    Official source

  3. Grant date recorded

    LRD23A0001

    Official source

  4. Notified commencement

    Commencement notice

    Construction of 114 no. 2 and 3 storey terraced dwellings and associated works at Citywest Avenue, Brownsbarn, Dublin 24.

    114 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of 6 no. duplex blocks comprising 84 no. units, consisting of 48 one-bedroom units and 36 three-bedroom units, ranging in height from 2-3 storeys and associated works at Citywest Avenue, Brownsbarn, Dublin 24.

    84 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of 4 no. apartment buildings comprising 178 apartments, creche and amenity areas, ranging in height from 5-7 storeys at Citywest Avenue, Brownsbarn, Dublin 24.

    178 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Construction of ESB Substation and associated site works located on Citywest Avenue, Brownsbarn, South Dublin.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.