Planning case 167031

Cork County Council · 167031 · Mogeely, Cork

Latest linked evidence

Notified commencement · 2019-05-08

Building 25 - Pasteurisation & RO Building

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    167031

    Official source

  2. Planning decision

    167031

    Conditional permission

    Official source

  3. Notified commencement

    Commencement notice

    Construction of a new cheese production facility - Predominately single storey building with a three storey middle section and a two storey administration block.

    Quantity not established for this notice.

    · Notice evidence

  4. Notified commencement

    Commencement notice

    New Dewatering & Control building at Dairygold Wastewater Treatment Plant (WwTP)

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of the following buildings; Building 27 – Firewater Pumphouse/Water Treatment/Electrical Building Building 28 – ESB Sub-Station & Switchrooms Building

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of the following buildings; Building 21 - Milk Intake Building Building 26 - Weighbridge Building

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Building 25 - Pasteurisation & RO Building

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.