Connected planning records

Planning case 1741

Galway City Council · 1741 · Galway, Galway

Latest linked evidence

Notified commencement · 2022-03-04

Fit out of New Hotel Development in existing part-two, part-three, part-four storey building over lower ground floor in 2no. blocks (the north-western block fronting Prospect Hill/ Bohermore) and the south-eastern block (located to the rear of the site) connected at all floor levels comprising of hotel guest bedrooms; bars; storage; associated signage; administration and staff facilities; plant; waste storage area and delivery and dispatch area with total gross floor area of 5250 sq.m.’ The works also include external landscaping; drainage connections; and minor completions to the external envelope.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    1741

  2. Planning decision

    1741

    Conditional permission

  3. Grant date recorded

    1741

  4. Notified commencement

    Commencement notice

    The development will consist of the: demolition of the existing single- storey commercial building at No.80 Prospect Hill; demolition of the existing two-storey dwelling at No.84 Bohermore; demolition of the existing part-single, part two-storey rear extension to No.86 Bohermore (a Protected Structure, Ref. 1201) and associated garden shed.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of a hotel on an overall site of 0.29 ha (0.73 acres). Construction of a part-two, part-three, part-four storey hotel over lower ground floor (with fourth floor level setbacks to the south-east) in 2No. blocks( the north-western block ( fronting Prospect Hill/ Bohermore) and the south-eastern block (located to the rear of the site) connected at all floor levels) comprising 139 No. bedrooms and related hotel facilities (including: reception area; lounge area; dining area; 2No. bars; storage; associated signage; administration and staff facilities; plant ( including substation with associated switch room); waste storage area; and delivery and dispatch area), with total gross floor area of 5,310 sq m (including lower ground level of 1,269 sq m). The development includes works to protect and conserve the older elements of No.86 Bohermore and also the existing former railway tunnel (located beneath No.80 Prospect Hill) that will be integrated into the overall proposal, which includes for a change of use of these areas from residential use and infrastructural use to hotel use, respectively. The development will also include the provisions of: vehicular and pedestrian access via Prospect Hill; 11 No. car parking spaces; associated lighting; associated site servicing (foul and surface water drainage and water supply); SUDs measures, including attenuation tank and sedum roofs; and gardens and courtyards. The scheme also includes: all hard and soft landscaping; boundary tr

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Fit out of New Hotel Development in existing part-two, part-three, part-four storey building over lower ground floor in 2no. blocks (the north-western block fronting Prospect Hill/ Bohermore) and the south-eastern block (located to the rear of the site) connected at all floor levels comprising of hotel guest bedrooms; bars; storage; associated signage; administration and staff facilities; plant; waste storage area and delivery and dispatch area with total gross floor area of 5250 sq.m.’ The works also include external landscaping; drainage connections; and minor completions to the external envelope.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.