Planning case D14B0243

Dun Laoghaire Rathdown County Council · D14B0243 · Monkstown, Dublin

Latest linked evidence

Notified commencement · 2014-12-27

Development consisting of construction of single storey extension to the side of existing dwelling with roof lights overhead, alteration of existing internal layout, construction of canopy to the front, re-construction of new windows and door to the existing front, side and rear elevations, alteration to elevations to match, construction of two storey extension over existing single storey section of house to front, changing of roof profile and placing of roof light in side roof profile and all ancillary site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    D14B0243

  2. Planning decision

    D14B0243

    Permission granted

  3. Grant date recorded

    D14B0243

  4. Notified commencement

    Commencement notice

    Development consisting of construction of single storey extension to the side of existing dwelling with roof lights overhead, alteration of existing internal layout, construction of canopy to the front, re-construction of new windows and door to the existing front, side and rear elevations, alteration to elevations to match, construction of two storey extension over existing single storey section of house to front, changing of roof profile and placing of roof light in side roof profile and all ancillary site works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.