Planning case 21380

Meath County Council · 21380 · Navan, Meath

Latest linked evidence

Notified commencement · 2023-06-14

Demolition of the existing practice wall and prefabricated classrooms and construction of a fully serviced two-storey extension to the existing school containing 5 Specialist classrooms, together with ancillary rooms; 6 general purpose classrooms; administration rooms, student facilities, plantroom, circulation space and associated works; internal and external, including landscaping. There will also be pedestrian and vehicular connections to the Meath County Council & Ride Facility (Part 8/20015). The works are proposed within the curtilage of a Recorded Protected Structure, NT25-172.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    21380

  2. Planning decision

    21380

    Conditional permission

  3. Grant date recorded

    21380

  4. Notified commencement

    Commencement notice

    Demolition of the existing practice wall and prefabricated classrooms and construction of a fully serviced two-storey extension to the existing school containing 5 Specialist classrooms, together with ancillary rooms; 6 general purpose classrooms; administration rooms, student facilities, plantroom, circulation space and associated works; internal and external, including landscaping. There will also be pedestrian and vehicular connections to the Meath County Council & Ride Facility (Part 8/20015). The works are proposed within the curtilage of a Recorded Protected Structure, NT25-172.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.