Connected planning records

Planning case D23A0206

Dun Laoghaire Rathdown County Council · D23A0206 · Killiney, Dublin

Latest linked evidence

Notified commencement · 2024-09-30

Erection of 1 No 2 storey 4 bedroom dwelling house circa 172 square metres net internal area approximately (circa 211 square metres gross external area approx) to include new vehicle access, car parking, new service and drainage connections and other associated site works on site comprising 0.0439 hectares (circa 439 square metres) at side of existing house

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    D23A0206

  2. Planning decision

    D23A0206

    Permission granted

  3. Notified commencement

    Commencement notice

    New vehicle access to site via Avondale Park, site clearance, demolition of existing side extension, excavation and laying of stone for foundation, excavation of new service and drainage connections to perimeter of property, erection of site perimeter fencing and gates

    Quantity not established for this notice.

    · Notice evidence

  4. Notified commencement

    Commencement notice

    Erection of 1 No 2 storey 4 bedroom dwelling house circa 172 square metres net internal area approximately (circa 211 square metres gross external area approx) to include new vehicle access, car parking, new service and drainage connections and other associated site works on site comprising 0.0439 hectares (circa 439 square metres) at side of existing house

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.