The signed 14 July further-information request leaves access, parking and water design unresolved for a 261 m² extension. Existing building areas and retained boundary works are distinct; the May drawings are planning submissions, not a grant or construction issue.
The 261 m² addition is separate from existing and retained work
May proposed extension and separate retention scope; July further information remains outstanding
What the evidence says
The ground and first-floor schedules distinguish 1,285 m² existing building from 261 m² proposed addition, giving 1,546 m² combined. Yellow outlines identify new showroom, van-loading, office and display-walkway areas. The application separately seeks retention of about 155 linear metres of existing boundary and two gates. Its description says approximately 6.5 m high; the elevation dimension is 6.13 m, so final height should be checked against the eventual approved drawing.
Why it may matter — interpretation
Commercial fit-out and building teams can distinguish the addition from the existing warehouse and retained boundary instead of pricing the combined total as new build.
What is not established
A final permission, reconciled approved height, structural design and installed facade products are not established.
Inspect the evidence
Signed request for further information · p.1
Development: 261 ... 6.5m ... retention ... 155 linear meters · Issued 2026-07-14 · Decision Order 0789; signed 14 July 2026; additional information required · Checked 2026-09-07
Development: 261 ... 6.5m ... retention ... 155 linear meters
Proposed ground floor and area schedule · p.1
EXISTING 1285; NEW PROPOSED 261; TOTAL 1546; yellow outline · Issued 2026-05-14 · D1297-3-13; issue date 14 May; revision blank; received 20 May; planning purposes only · Checked 2026-09-07
EXISTING 1285; NEW PROPOSED 261; TOTAL 1546; yellow outline
Proposed first floor and display walkway · p.1
VOID; DISPLAY WALKWAY; proposed yellow outline · Issued 2026-05-14 · D1297-3-14; issue date 14 May; revision blank; received 20 May; planning purposes only · Checked 2026-09-07
VOID; DISPLAY WALKWAY; proposed yellow outline
Proposed elevations and sections · p.1
PROPOSED; EXISTING; 6130 elevation dimension · Issued 2026-05-14 · D1297-3-15; issue date 14 May; revision blank; received 20 May; planning purposes only · Checked 2026-09-07
PROPOSED; EXISTING; 6130 elevation dimension
Parking and large-vehicle movements need revised drawings
Roads information requested on 14 July
What the evidence says
FI item 1 requires parking and bicycle layouts at not less than 1:200, with calculations covering all proposed uses and floorspace, including warehouse and office. It also requires swept paths demonstrating access and exit for fire tenders and large refuse vehicles. The May 1:500 site plan shows parking and existing entrances but does not close that later request.
Why it may matter — interpretation
Transport and civil designers need an integrated service-vehicle and parking layout before treating the site arrangement as settled.
What is not established
A revised submission, council acceptance and agreed parking or bicycle counts were not found in the reviewed catalogue.
Inspect the evidence
Signed request for further information · p.1
1. Access and Parking (a)-(b) · Issued 2026-07-14 · Decision Order 0789; signed 14 July 2026; additional information required · Checked 2026-09-07
1. Access and Parking (a)-(b)
Signed request for further information · p.2
(c) swept path analysis; all proposed uses/floor space · Issued 2026-07-14 · Decision Order 0789; signed 14 July 2026; additional information required · Checked 2026-09-07
(c) swept path analysis; all proposed uses/floor space
Proposed site layout and existing entrances · p.1
SITE LAYOUT 1:500; EXISTING SITE ACCESS · Issued 2026-05-14 · D1297-3-03; issue date 14 May; revision blank; received 20 May; planning purposes only · Checked 2026-09-07
SITE LAYOUT 1:500; EXISTING SITE ACCESS
Surface-water calculations and a SuDS design remain required
Unresolved drainage and attenuation request dated 14 July
What the evidence says
FI item 2 requests drainage plans and sections through the public sewer connection, maximum discharge in litres per second, and attenuation volumes based on surface areas and runoff coefficients. It requires SuDS and expressly says underground attenuation tanks are not permitted. The listed green roofs, swales and other measures are examples, not selected installed systems.
Why it may matter — interpretation
Drainage designers need the runoff model, discharge constraint and accepted above-ground or source-control arrangement before selecting products.
What is not established
Accepted discharge rate, storage volume, chosen SuDS components and completed drainage are not established.
Inspect the evidence
Signed request for further information · p.2
2. Water Services (a)-(c); Underground attenuation tanks are not permitted · Issued 2026-07-14 · Decision Order 0789; signed 14 July 2026; additional information required · Checked 2026-09-07
2. Water Services (a)-(c); Underground attenuation tanks are not permitted
The extension must be coordinated with a 150 mm watermain
Existing utility constraint identified in the information request
What the evidence says
The July water-services note identifies an existing 150 mm watermain to the north, east and south of the site and asks the applicant to consult Uisce Eireann about the building setback. The proposed extension is on the north and east of the existing building.
Why it may matter — interpretation
Utility and structural teams should resolve the main alignment and setback before fixing foundations and external works.
What is not established
A surveyed main route, agreed setback, diversion requirement or Uisce Eireann acceptance was not reviewed.
Inspect the evidence
Signed request for further information · p.2
existing 150mm diameter watermain ... North, East and South ... setback · Issued 2026-07-14 · Decision Order 0789; signed 14 July 2026; additional information required · Checked 2026-09-07
existing 150mm diameter watermain ... North, East and South ... setback
Proposed ground floor and area schedule · p.1
PROPOSED STRUCTURES OUTLINED IN YELLOW · Issued 2026-05-14 · D1297-3-13; issue date 14 May; revision blank; received 20 May; planning purposes only · Checked 2026-09-07
PROPOSED STRUCTURES OUTLINED IN YELLOW
The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.