Save this project to account
Connected planning records

Planning case 19895

Clare County Council · 19895 · Parteen, Clare

Latest linked evidence

Notified commencement · 2025-03-18

1.2.1 The development comprises of the refurbishment of the existing nursing home building into a new Dual Diagnosis facility and Child & Adolescent Mental Health Services (CAMHS) facility respectively. The refurbishment works will also include the Training Area, which has its own external entrance. The works will also include the demolition of existing external concrete stairway, which serves a first-floor storage room, and the provision of new dormer roof entrance accessed via a new external steel stair. Site works include the creation of a new entrance area for the CAMHS facility, a new turning and set down area and additional parking, all to the rear of the site. New line marking will be provided for parking spaces and to demarcate the pedestrian route. Landscape works include tidying up of existing and providing new planting around the new CAMHS entrance. 1.2.2 There will be energy upgrade works to the existing building, including new external insulated render to the external walls, new triple glazed windows and new attic insulation.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    19895

  2. Planning decision

    19895

    Conditional permission

  3. Grant date recorded

    19895

  4. Notified commencement

    Commencement notice

    1.2.1 The development comprises of the refurbishment of the existing nursing home building into a new Dual Diagnosis facility and Child & Adolescent Mental Health Services (CAMHS) facility respectively. The refurbishment works will also include the Training Area, which has its own external entrance. The works will also include the demolition of existing external concrete stairway, which serves a first-floor storage room, and the provision of new dormer roof entrance accessed via a new external steel stair. Site works include the creation of a new entrance area for the CAMHS facility, a new turning and set down area and additional parking, all to the rear of the site. New line marking will be provided for parking spaces and to demarcate the pedestrian route. Landscape works include tidying up of existing and providing new planting around the new CAMHS entrance. 1.2.2 There will be energy upgrade works to the existing building, including new external insulated render to the external walls, new triple glazed windows and new attic insulation.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.