Save this project to account
Connected planning records

Planning case 2237

Meath County Council · 2237 · Laytown, Meath

Latest linked evidence

Notified commencement · 2022-07-08

SN0007447MH · The proposed development of a new main school building with 24 classrooms and a Special Educational Needs Unit for Scoil an Spioraid Naoimh, Laytown. The development at ground floor will comprise of 10 No. General Classrooms with a respective WC, an Admin Office, Principal’s Office, a Multi-Purpose Room, 2 General Purpose Rooms, 2 Servery’s, 2 Class Base’s, Multi-Sensory Room, a Para-Ed Room, multiple Sanitary Facilities and stores. First floor will comprise of 14 No. General Classrooms, a Library, a Staff Room, a Resource Room, multiple WCs and associated storage spaces.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2237

  2. Planning decision

    2237

    Conditional permission

  3. Grant date recorded

    2237

  4. Notified commencement

    SN0007447MH

    The proposed development of a new main school building with 24 classrooms and a Special Educational Needs Unit for Scoil an Spioraid Naoimh, Laytown. The development at ground floor will comprise of 10 No. General Classrooms with a respective WC, an Admin Office, Principal’s Office, a Multi-Purpose Room, 2 General Purpose Rooms, 2 Servery’s, 2 Class Base’s, Multi-Sensory Room, a Para-Ed Room, multiple Sanitary Facilities and stores. First floor will comprise of 14 No. General Classrooms, a Library, a Staff Room, a Resource Room, multiple WCs and associated storage spaces.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.