Save this project to account
Connected planning records

Planning case F17A0184

Fingal County Council · F17A0184 · Ballyboughal, Dublin

Latest linked evidence

Notified commencement · 2019-02-01

SN0003900FL · Construction of a new 2 storey commercial unit together with associated site works at Cnoc Dubh, Ballyboughal, Co. Dublin

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    F17A0184

    Official source

  2. Planning decision

    F17A0184

    Permission granted

    Official source

  3. Grant date recorded

    F17A0184

    Official source

  4. Notified commencement

    CN0036782FL

    Demolition of unfinished structures and construction of site civil works (services, road and footpaths).

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    CN0038144FL

    Construction of 20 No. 2 Storey Houses at Sites 1,3,5 & 7 The Walk, 5-9 & 14-21 The Green, 1 The View and 1 & 2 The Lawn, Cnoc Dubh, Ballyboughal, Co. Dublin.

    20 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    CN0039678FL

    Construction of 37 No. Dwellings at sites at 2-5 the View, 3-12 The Lawn, 1-4 The Crescent, 1-3 the Close, 1-3 & 10-13 The Green, 2, 4, 6, 8-10 The Walk, and 1-3 the Square, Cnoc Dubh, Ballyboughal, Co. Dublin.

    37 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    SN0003900FL

    Construction of a new 2 storey commercial unit together with associated site works at Cnoc Dubh, Ballyboughal, Co. Dublin

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.