Planning case 211221

Meath County Council · 211221 · College, Nobber, Meath

Latest linked evidence

Notified commencement · 2022-07-25

SN0007514MH · The development will consist of the extension to the existing Biodiesel Manufacturing Facility across all 3 no. floor levels resulting in an increased floor area of c. 354sqm; the provision of an external stairs; the provision of an off-loading bund area and all ancillary site development works above and below ground.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    211221

  2. Planning decision

    211221

    Conditional permission

  3. Grant date recorded

    211221

  4. Notified commencement

    SN0007514MH

    The development will consist of the extension to the existing Biodiesel Manufacturing Facility across all 3 no. floor levels resulting in an increased floor area of c. 354sqm; the provision of an external stairs; the provision of an off-loading bund area and all ancillary site development works above and below ground.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.