Planning case 2460829

Tipperary County Council · 2460829 · Thurles, Tipperary

Latest linked evidence

Notified commencement · 2026-02-02

The construction of the provision of a 478.8 sq. m. single storey drive-thru restaurant. The development will also include the provision of a site access from the existing access road the Lidl and Insomnia units to the north of the proposed development and free-standing structures for the drive-thru restaurant including a height restrictor and customer order points with canopies. An outdoor seating area, coral area including bin and general storage, plant infrastructure works, and all associated site works above and below ground.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2460829

  2. Planning decision

    2460829

    Conditional permission

  3. Notified commencement

    Commencement notice

    The construction of the provision of a 478.8 sq. m. single storey drive-thru restaurant. The development will also include the provision of a site access from the existing access road the Lidl and Insomnia units to the north of the proposed development and free-standing structures for the drive-thru restaurant including a height restrictor and customer order points with canopies. An outdoor seating area, coral area including bin and general storage, plant infrastructure works, and all associated site works above and below ground.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.