Planning case 2360290

Meath County Council · 2360290 · Dunboyne, Meath

Latest linked evidence

Notified commencement · 2026-07-07

Construction of a new Creche (BX01 - Shell and core works only) and associated site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

W32 contains two pending LRD appeals lodged7August2026. The May2026 amendment report describes124 apartments replacing76 in Phase1, yielding315 rather than267+124. Its account of earlier permissions/construction is a dated consultant statement in the official file, not an independent current permission/completion check.

1 official documents inspected · Checked 2026-09-05 · Official file index

124 apartments replace76; proposed Phase1 total315

Proposed amendment; outcome pending · Phase1 apartment amendment under2660607, within the earlier2360290 scheme

What the evidence says
The amendment replaces76 apartments with124 in BlocksA/B/C, an increase of48. Table2 changes the overall Phase1 total from267 to315 while145 houses remain unchanged.

Why it may matter — interpretation
Interpretation for designers and quantity surveyors: scope the48-unit increase and revised apartment mix; do not treat all124 as additional dwellings.

What is not established
Both current appeals are pending. The final approved unit schedule, installed works and procurement availability are not established. Inspect the eventual orders and reconciled schedule.

Inspect the evidence

EIAR Addendum Report: Dunboyne Phase 1 Amendment · p.7
Inspected PDF page 7 · Issued May 2026 (month only) · RevisionA, submitted; stamped received21May2026 · Checked 2026-09-05

267 no. units / 315 no. units / +48

The amendment changes parking and cycle provision

Proposed amendment; outcome pending · Overall Phase1 comparison table in the May2026 apartment amendment

What the evidence says
Table2 changes Phase1 parking from357 to366 spaces (+7 standard and+2 GoCar), and cycle parking from649 to671 (+30 secure,−8 visitor); the280m²/65-place creche is unchanged.

Why it may matter — interpretation
Interpretation for civil and cycle-parking suppliers: the revised provision identifies specific layout/equipment scope to compare with the approved drawings.

What is not established
No equipment appointment or installed counts are proven. Confirm the final parking/landscape schedule after the appeals.

Inspect the evidence

EIAR Addendum Report: Dunboyne Phase 1 Amendment · p.8
Inspected PDF page 8 · Issued May 2026 (month only) · RevisionA, submitted; stamped received21May2026 · Checked 2026-09-05

357 no. car spaces / 366 no. car spaces
Remaining document questions
  • Both current appeals are pending. The final approved unit schedule, installed works and procurement availability are not established. Inspect the eventual orders and reconciled schedule.
  • No equipment appointment or installed counts are proven. Confirm the final parking/landscape schedule after the appeals.

ACP324557 links one92-page EIAR addendum; selected pages5,7,8 visually inspected. ACP324555 currently links noPDF. No whole-file or construction/compliance review. Issue monthMay2026 is preserved; received stamp21May2026 is distinct.

Source history

Timeline

  1. Planning application received

    2360290

  2. Planning decision

    2360290

    Conditional permission

  3. Notified commencement

    Commencement notice

    Construction of a new Creche (BX01 - Shell and core works only) and associated site works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.