Connected planning records

Planning case 2660008

Laois County Council · 2660008

Latest linked evidence

Commission case decision · 2026-08-18

324341 · Appeal withdrawn

Open official source

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

The final grant signed 31 August explicitly permits 217 residential units with commercial buildings, following the appeal withdrawal notified in August. The retained headline of 76 is not the whole permission described in condition 1(c); selected quantities remain unchanged pending separate reconciliation. Phase delivery and substantial pre-commencement infrastructure conditions apply.

3 official documents inspected · Checked 2026-09-07 · Official file index

Final permission explicitly covers 217 homes after appeal withdrawal

Final permission after a withdrawn appeal; whole-permission quantity distinguished from retained headline

What the evidence says
The final grant signed 31 August covers 217 residential units and two mixed-use commercial buildings. Condition 1(c) expressly fixes the permitted residential total at 217; the description divides it into 74 houses, 141 apartments and duplexes, and two assisted-living units. The Commission letter dated 21 August notifies withdrawal of appeal ACP-324341-26. The retained 76-home headline is not established as the full permission total by these documents and is left unchanged for separate reconciliation.

Why it may matter — interpretation
Housing, commercial and infrastructure teams can assess the permitted project without treating a partial retained count as its full scale.

What is not established
Construction commencement, occupation and reconciliation of the retained headline quantity are not established.

Inspect the evidence

Final grant and twenty-eight conditions · p.1
217 residential units: 74 houses, 141 apartments/duplexes and two assisted-living units · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

217 residential units: 74 houses, 141 apartments/duplexes and two assisted-living units

Final grant and twenty-eight conditions · p.2
Final grant signed 31 August 2026 · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Final grant signed 31 August 2026

Final grant and twenty-eight conditions · p.4
Condition 1(c): total residential units granted is 217 · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 1(c): total residential units granted is 217

Commission notification of appeal withdrawal · p.1
ACP-324341-26 withdrawal notified 21 August 2026; council reference2660008 · Issued 2026-08-21 · ACP-324341-26; letter dated 21 August, council received 24 August 2026 · Checked 2026-09-07

ACP-324341-26 withdrawal notified 21 August 2026; council reference2660008

The creche belongs in phase one and utility agreements precede works

Final-grant phase and utility dependencies

What the evidence says
Condition 12 requires the approved creche to be delivered in phase one, following the January phasing plan. Condition 3 requires a signed Uisce Eireann agreement before commencement and written feasibility and approval for service diversions or building over existing services. Potable water must be available before first occupation and foul effluent must connect to the public foul sewer.

Why it may matter — interpretation
The first-phase programme must include the creche and coordinate service agreements and diversions before mobilisation.

What is not established
Phase commencement, a completed creche, signed utility agreements and accepted diversion designs are not established.

Inspect the evidence

Final grant and twenty-eight conditions · p.8
Condition 12: creche delivered in Phase 1 · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 12: creche delivered in Phase 1

Final grant and twenty-eight conditions · p.4
Condition 3: connection agreement and approved service diversions before works · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 3: connection agreement and approved service diversions before works

Off-site crossings and active-travel links are required before occupation

Final-grant external road and active-travel delivery obligations

What the evidence says
Condition 21 requires agreed designs for the Harpur’s Lane entrance raised table, pedestrian crossing and road-surface upgrade, and active-travel works along Harpur’s Lane and from Portlaoise College to the railway bridge on the R445. The specified crossing and active-travel schemes must be delivered before first occupation. Road-opening permission and a stage-three road-safety audit with remedial works are also required at their stated stages.

Why it may matter — interpretation
Civil and traffic teams should include works outside the red-line housing plots and their approval and handover sequence.

What is not established
Agreed detailed designs, road-opening permission, completed links and accepted safety audits are not established.

Inspect the evidence

Final grant and twenty-eight conditions · p.11
Condition 21(b)–(d): road opening and road-safety audits · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 21(b)–(d): road opening and road-safety audits

Final grant and twenty-eight conditions · p.12
Condition 21(i)–(j): raised table and crossing with road-surface upgrade · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 21(i)–(j): raised table and crossing with road-surface upgrade

Final grant and twenty-eight conditions · p.13
Condition 21(p)–(q): R445 and Harpur’s Lane active-travel schemes before occupation · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 21(p)–(q): R445 and Harpur’s Lane active-travel schemes before occupation

Permeable paving and the northern drain need revised agreed details

Later final-grant conditions qualify the submitted FI drawing

What the evidence says
The April revision C site drawing specifies a no-infiltration permeable-pavement system and shows the northern culvert interface. The later grant requires a revised permeable-paving design including drainage, a surface-water diversion to the Harpur’s Lane crossing, and a maintainable two-stage rake screen, channel and overflow weir at the northern drain. It also requires the southwestern culvert extension and omission of the northern-access chicane. The submitted details are therefore subject to further coordinated design.

Why it may matter — interpretation
Drainage and paving contractors need the agreed revisions before fixing pavement build-ups, culvert works and entrance details.

What is not established
Accepted revised pavement, diversion and screen designs, installed works and compliance sign-off are not established.

Inspect the evidence

Further-information site layout and pavement details · p.1
P3553-C001 C: permeable pavement System C, no infiltration, and northern culvert interface · Issued 2026-04-20 · P3553-C001 revision C; FI response issue 20 April, received 27 April 2026 · Checked 2026-09-07

P3553-C001 C: permeable pavement System C, no infiltration, and northern culvert interface

Final grant and twenty-eight conditions · p.12
Condition 21(l): revised permeable-paving design including drainage · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 21(l): revised permeable-paving design including drainage

Final grant and twenty-eight conditions · p.13
Condition 21(n)–(o), (r) and (t): diversion, screens, culvert extension and omit chicane · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 21(n)–(o), (r) and (t): diversion, screens, culvert extension and omit chicane

Ten percent of parking needs working chargers, with ducting for the remainder

Final-grant charging and lighting obligations

What the evidence says
Condition 18 requires functioning EV charging at ten percent of all car-parking spaces and ducting for the remaining spaces, with an agreed ducting layout before commencement. Condition 20 requires a revised agreed public-lighting design using LED luminaires with a minimum ten-year warranty. These are delivery requirements rather than evidence of installed equipment.

Why it may matter — interpretation
Electrical teams can distinguish initial charger installation from future charging provision and coordinate both with public-lighting design.

What is not established
Installed charger counts or power ratings, agreed ducting layout and commissioned lighting are not established.

Inspect the evidence

Final grant and twenty-eight conditions · p.10
Condition 18(b): ten percent functioning EV points, ducting all remaining spaces · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 18(b): ten percent functioning EV points, ducting all remaining spaces

Final grant and twenty-eight conditions · p.11
Condition 20: revised LED lighting report and minimum ten-year warranty · Issued 2026-08-31 · Final grant signed 31 August 2026; 28 conditions · Checked 2026-09-07

Condition 20: revised LED lighting report and minimum ten-year warranty
Remaining document questions
  • Have the phase-one creche programme, utility agreements, active-travel schemes and revised drainage designs been agreed?

The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.