Planning case 22302

Galway County Council · 22302 · Aille West, Galway

Latest linked evidence

Notified commencement · 2026-08-26

Application for the development works on a 1.76ha/4.35 acres site at Colaiste Cholmcille, Inverin, Co. Galway. The development will consist of (i) school building extension (4,368sqm) over 3 levels. Incorporating classrooms, specialist teaching spaces, social spaces, multi-purpose hall, special education needs unit, reception, offices and ancillary accommodation. Services to include roof mounted photovoltaic panels, boiler, ESB substation kiosk and gas compound. (ii) The refurbishments to existing school building c1955, c1990 & c2013 (1184sqm). (iii) The demolition of two ancillary buildings (c1950s) and the existing prefab accommodation on the site. (iv) New site entrances & internal access roadway with set down area, car parking for 45no. spaces (including 1no. EV Charging point), 2no. covered bicycle stands, 1no. ballcourt, site lighting, new wastewater treatment system and percolation area, new site boundaries treatments and all ancillary site works. Gross floor space of proposed works: 4368sqm. in the townland of Na hAille, Inverin, Co. Galway

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

The retained council grant is dated 22 August 2022. A later cover letter, dated 11 August 2026 and stamped received on 13 August, submits four contractor compliance plans. The documents do not establish council acceptance of every pre-start detail or completed construction.

2 official documents inspected · Checked 2026-09-05 · Official file index

Extension and refurbishment are separate quantities

Granted condition; detail fulfilment not established · Galway County 22/302: extension and existing-school refurbishment

What the evidence says
The final grant dated 22 August 2022 describes a 4,368 sqm school extension over three levels and refurbishment of 1,184 sqm of existing buildings. It also includes roof-mounted PV, a boiler, gas compound and an ESB substation kiosk. These figures are not a new combined building total.

Why it may matter — interpretation
Interpretation: preserves the different construction scopes in the granted description.

What is not established
Current installed quantities, selected equipment and completion of every permitted element are not established.

Inspect the evidence

Final grant and 22 conditions · p.1
school building extension (4,368sqm) · Issued 2022-08-22 · Signed 22 August 2022; portal upload field says 19 August 2022 and is not used as the issue date · Checked 2026-09-05

school building extension (4,368sqm)

The grant leaves detailed cladding choices for written agreement

Granted condition; detail fulfilment not established · 2022 grant conditions for the school extension

What the evidence says
Condition 3 specifies nap plaster where shown, permits aluminium, timber or non-white uPVC windows, and requires written agreement of wall and roof cladding details. The condition does not identify one selected cladding product.

Why it may matter — interpretation
Interpretation: separates consent requirements from a final material schedule.

What is not established
The later written cladding agreement, manufacturer and installed finishes are not established.

Inspect the evidence

Final grant and 22 conditions · p.2
nap plaster finish · Issued 2022-08-22 · Signed 22 August 2022; portal upload field says 19 August 2022 and is not used as the issue date · Checked 2026-09-05

nap plaster finish

The grant identifies biological treatment and a polishing filter

Granted condition; detail fulfilment not established · School foul drainage and pumping infrastructure under the 2022 grant

What the evidence says
Condition 8 specifies an on-site BAF wastewater treatment system with a tertiary sand polishing filter. Condition 9 requires pumping-station and network specifications before commencement. The grant supplies the system type, not proof of its commissioning.

Why it may matter — interpretation
Interpretation: identifies the wastewater package while retaining the detail-approval requirement.

What is not established
Selected manufacturer, design flow, later agreed pump specifications and commissioning are not established.

Inspect the evidence

Final grant and 22 conditions · p.2
onsite BAF wastewater treatment system · Issued 2022-08-22 · Signed 22 August 2022; portal upload field says 19 August 2022 and is not used as the issue date · Checked 2026-09-05

onsite BAF wastewater treatment system

August 2026 documents record a compliance submission

Compliance submission received; acceptance not established · Recent submission against the existing permission, distinct from final consent and physical commencement

What the evidence says
The 11 August 2026 cover letter submits contractor plans for conditions 18, 20, 21 and 22, covering traffic, construction environmental management and waste. It is stamped received on 13 August; the portal lists upload on 18 August. It is not the council's written acceptance of those plans.

Why it may matter — interpretation
Interpretation: adds a dated pre-start milestone without turning submission into approval.

What is not established
Council acceptance of all four plans, the final works programme and completed site work are not established.

Inspect the evidence

Cover letter submitting contractor compliance plans · p.1
Planning Conditions requiring written agreement · Issued 2026-08-11 · Dated 11 August 2026; received stamp 13 August; portal upload 18 August · Checked 2026-09-05

Planning Conditions requiring written agreement
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 2 government-published PDFs were visually inspected. The index has 40 public file links. Five PDFs were accessed; two support these findings. Selected pages of the construction plan and the ecology-report covers were also screened but add no published technical claim. Restricted personal-information rows were not accessed. Proposals do not establish procurement or installed work.

Source history

Timeline

  1. Planning application received

    22302

  2. Planning decision

    22302

    Conditional permission

  3. Grant date recorded

    22302

  4. Notified commencement

    Commencement notice

    Application for the development works on a 1.76ha/4.35 acres site at Colaiste Cholmcille, Inverin, Co. Galway. The development will consist of (i) school building extension (4,368sqm) over 3 levels. Incorporating classrooms, specialist teaching spaces, social spaces, multi-purpose hall, special education needs unit, reception, offices and ancillary accommodation. Services to include roof mounted photovoltaic panels, boiler, ESB substation kiosk and gas compound. (ii) The refurbishments to existing school building c1955, c1990 & c2013 (1184sqm). (iii) The demolition of two ancillary buildings (c1950s) and the existing prefab accommodation on the site. (iv) New site entrances & internal access roadway with set down area, car parking for 45no. spaces (including 1no. EV Charging point), 2no. covered bicycle stands, 1no. ballcourt, site lighting, new wastewater treatment system and percolation area, new site boundaries treatments and all ancillary site works. Gross floor space of proposed works: 4368sqm. in the townland of Na hAille, Inverin, Co. Galway

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.