South Dublin County Council · SHD3ABP30239818 · Citywest, Dublin
Latest linked evidence
Notified commencement · 2020-05-27
CN0064468SD · As part of the proposed new residential development at The Quarter at Citywest, Cooldown Commons, Citywest, Dublin 24, a new ESB substation will be constructed on the same site.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.
123 units (Phase 1) of a residential development containing 459 permitted residential units, comprising of 294 apartments over 5 no. blocks, 42 no. duplex units and 123 no. terraced, semi-detached and detached two and three storey houses, a creche facility and all associated ancillary works.
123 units stated for this notice or phase; not a project total.
The proposed project consists of the construction of a three (3) storey residential development containing five (5) duplex units and five (5) single storey apartment units.
10 units stated for this notice or phase; not a project total.
It is proposed to construct a residential development in The Quarter at Citywest (Phase 2), Cooldown Commons, Citywest, Dublin 24. The development will consist of 3 residential blocks (A1, A2, & A3) above a shared basement level (incorporating car parking, storage and plant areas). It is proposed that all blocks will consist of 6 storeys of open plan residential apartments respectively, each served by a single escape stair.
135 units stated for this notice or phase; not a project total.
It is proposed to construct a residential development at the Quarter at Citywest (Phase 2), Cooldown Commons, Citywest, Dublin 24. This application relates to Block B1 which is a six story apartment building containing 48 apartment units.The overall development consist of six residential blocks, three of which, (A1, A2 & A3) are over a basement carpark.
48 units stated for this notice or phase; not a project total.
It is proposed to construct a residential development at The Quarter at Citywest (Phase 2), Cooldown Commons, Citywest, Dublin 24. This application relates to Block B2 which is a six story apartment building containing 52 apartment units.The overall development consist of six residential blocks, three of which, (A1, A2 & A3) are over a basement carpark.
52 units stated for this notice or phase; not a project total.
It is proposed to construct a residential development at The Quarter at Citywest (Phase 2), Cooldown Commons, Citywest, Dublin 24. This application relates to Block B3 which is a six story apartment building containing 47 apartment units. The overall development consist of six residential blocks, three of which, (A1, A2 & A3) are over a basement carpark.
47 units stated for this notice or phase; not a project total.
It is proposed to construct a new four story apartment (Block C) building at The Quarter at Citywest, Cooldown Commons, Citywest, Dublin 24. The block shall be served by a single escape stair.
14 units stated for this notice or phase; not a project total.
As part of the proposed new residential development at The Quarter at Citywest, Cooldown Commons, Citywest, Dublin 24, a new ESB substation will be constructed on the same site.
Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.