Galway City Council · 1810 · Galway, Galway

Latest linked evidence

Notified commencement · 2020-08-04

Construction of a new building: 2 storey 110kV Gas Insulated Switchgear (GIS) building and associated site works at: ESB Galway 110 kV Substation, Ballybane Industrial Estate, Bothar na Mine, Galway.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    1810

  2. Planning decision

    1810

    Conditional permission

  3. Grant date recorded

    1810

  4. Notified commencement

    Commencement notice

    Proposed development at this stage of the works includes the construction of the internal palisade fence, new palisade gate to the public roadway, new temporary construction stone road, diversion of existing MV cables, demolition of existing equipment plinths and building and site investigation works for the design of the GIS building only. Note only building works is the demolition of the existing MV building

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of a new building: 2 storey 110kV Gas Insulated Switchgear (GIS) building and associated site works at : ESB Galway 110 kV Substation, Ballybane Industrial Estate, Bothar na Mine, Galway.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.