  1. Planning application received

    19437

  2. Planning decision

    19437

    Conditional permission

  3. Grant date recorded

    19437

  4. Notified commencement

    Commencement notice

    The development of an Advance Technology Building for IDA Ireland, designed to provide high quality production and office accommodation, which will accommodate future manufacturing/technological businesses. The construction will include reinforced Concrete (RC) foundations and ground floor slab, blockwork and RC rising walls, steelwork frame, composite metal cladding and curtain wall glazing, RC and blockwork walls and partitions, Composite floors and stairs, glazing and doors, M+E installations, lifts and associated siteworks. The unit will be completed to Category A level fit-out in the open production areas and in the office areas. The site is located at IDA Site, Dublin Road, Rathnapish, Carlow and the building will have an approximate gross floor area of 2,930 m2.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    ESB Substation and switchroom for IDA ATB Carlow

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.