Save this project to account
Connected planning records

Protected structure, John St, Ardee, Co. Louth - Planning Application 2560141

Louth County Council · 2560141 · Louth

Latest linked evidence

Notified commencement · 2025-07-08

A two storey extension to the south and west elevations of the existing factory, incorporating first floor offices and ground floor factory extension. A small single storey infill extension to the existing canteen to the south elevation, upgrading the existing south elevation with new cladding to match proposed finishes, together with all ancillary and associated site development works at our existing premises at John Street, Ardee, Co. Louth. The development is within the confines of a protected structure Ref LHS017-063.

Indexed observation: Granted. Read the linked decisions for their full terms.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2560141

  2. Planning decision

    2560141

    Conditional permission

  3. Grant date recorded

    2560141

  4. Notified commencement

    Commencement notice

    A two storey extension to the south and west elevations of the existing factory, incorporating first floor offices and ground floor factory extension. A small single storey infill extension to the existing canteen to the south elevation, upgrading the existing south elevation with new cladding to match proposed finishes, together with all ancillary and associated site development works at our existing premises at John Street, Ardee, Co. Louth. The development is within the confines of a protected structure Ref LHS017-063.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.