Save this project to account
Connected planning records

Planning case SD21A0200

South Dublin County Council · SD21A0200 · Rathcoole, Dublin

Latest linked evidence

Notified commencement · 2023-01-20

SN0008040SD · Construction of the Sprinkler System Pumphouse serving Site C at College Lane, Greenogue, Rathcoole, Co. Dublin and all associated site development works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    SD21A0200

    Official source

  2. Planning decision

    SD21A0200

    Permission granted

    Official source

  3. Grant date recorded

    SD21A0200

    Official source

  4. Notified commencement

    SN0007390SD

    Proposed construction of a large single-storey warehouse building with 3no. mezzanine floors. A two (2) storey ancillary office block is included on the (south) elevation, a two (2) storey ancillary office block is included on the (west) elevation. There is also a three (3) storey plant room located on the south elevation at Site C, College Lane, Greenogue, Rathcoole, Co. Dublin for Jordanstown Properties Ltd.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    SN0007993SD

    Construction of ESB sub-station serving Site C at College Lane, Greenogue, Rathcoole, Co. Dublin and all associated site development works.

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    SN0008040SD

    Construction of the Sprinkler System Pumphouse serving Site C at College Lane, Greenogue, Rathcoole, Co. Dublin and all associated site development works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.