Planning case 2660003

Cavan County Council · 2660003

Latest linked evidence

Planning appeal received · 2026-08-13

501871

Open official source

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

Cavan conditionally decided to grant permission on 22 July 2026. Commission case 501871, lodged 13 August 2026, remains pending. The retained cohort also contains case 501825, whose invalid status does not terminate the separate active appeal. The proposal term and council condition differ.

2 official documents inspected · Checked 2026-09-05 · Official file index

The assessment describes Phase 2 as 21.9 MWp, without battery storage

Proposed in application · Cavan 2660003, solar PV Phase 2; no count or capacity added from another phase

What the evidence says
The further-information fire assessment identifies Mannok solar PV Phase 2 as 21.9 MWp and states that it includes no energy storage. The council decision describes three 11 kV transformer stations. The assessment table calls its figure installed capacity, but this is a planning-stage design statement and does not establish commissioning.

Why it may matter — interpretation
Interpretation for solar and electrical work: separates this generation proposal from battery-storage schemes and identifies the source-stated design scale.

What is not established
No selected module or inverter model, commissioned capacity, grid agreement or built installation is established.

Inspect the evidence

Phase 2 fire-risk and firefighting water assessment · p.4
21.9 MWp · Issued April 2026 (month only) · Version 1.0 DRAFT dated 31 March; assessment 30 March; page footers show 1 and 15 April 2026; received 16 June 2026 · Checked 2026-09-05

21.9 MWp

Council notification and conditions · p.1
3 Transformer stations · Issued 2026-07-22 · Decision under appeal; proposal description and conditioned term retained separately · Checked 2026-09-05

3 Transformer stations

The council condition changes the proposed 40-year term to 35 years

Council decision under appeal · Council decision on Cavan 2660003; operational term under appeal

What the evidence says
The proposal description requests 40 years of operation. The council notification dated 22 July 2026 instead conditions a 35-year term from commissioning, with removal and restoration requirements. Active Commission appeal 501871 is pending; earlier case 501825 is separately marked invalid. Neither an issued final grant nor commissioning is established.

Why it may matter — interpretation
Interpretation: the condition controls the council-stage term, so the older 40-year headline should not be presented as the approved duration.

What is not established
No final appeal determination, construction start, actual commissioning date or fulfilled restoration condition is established.

Inspect the evidence

Council notification and conditions · p.1
40-year operation · Issued 2026-07-22 · Decision under appeal; proposal description and conditioned term retained separately · Checked 2026-09-05

40-year operation

Council notification and conditions · p.3
35 years · Issued 2026-07-22 · Decision under appeal; proposal description and conditioned term retained separately · Checked 2026-09-05

35 years

The fire strategy relies on existing hydrants rather than a dedicated on-site tank

Proposed in application · Further-information fire assessment for Phase 2, received 16 June 2026

What the evidence says
The assessment proposes no dedicated on-site firefighting water storage. It relies on the adjoining cement facility hydrant network and identifies a quarry sump as a backup. The report states a tested hydrant flow of at least 1,500 litres per minute at 2 bar, and proposes inverter protection and SCADA alarms. These are report statements, not independent certification of present availability or safety.

Why it may matter — interpretation
Interpretation for fire and water infrastructure: identifies reliance on existing infrastructure and the need to verify the final agreed response arrangements.

What is not established
Current flow, final fire-service approval, procurement and any later water-storage revision are not established. The page describes approximate distances differently in its table and narrative; no reconciled distance is published.

Inspect the evidence

Phase 2 fire-risk and firefighting water assessment · p.7
No dedicated on-site fire-fighting water storage · Issued April 2026 (month only) · Version 1.0 DRAFT dated 31 March; assessment 30 March; page footers show 1 and 15 April 2026; received 16 June 2026 · Checked 2026-09-05

No dedicated on-site fire-fighting water storage
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 2 government-published PDFs were visually inspected. The council index has 281 parsed document rows. 4 PDFs were accessed; selected visually reviewed pages of 2 support these findings. The remaining catalogue has not been fully inspected. Proposals do not establish procurement or installed work.

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.