Planning case 2360229

Kildare County Council · 2360229 · Rathangan, Kildare

Latest linked evidence

Notified commencement · 2026-07-24

SN0014503KE · Construction of 1block comprising 4no. dwellings (maisonettes) forming phase 2c of 3 to include house numbers 87-90 (Units 41-44)

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    2360229

  2. Planning decision

    2360229

    Conditional permission

  3. Grant date recorded

    2360229

  4. Notified commencement

    CN0136982KE

    Construction of 35no. dwellings and creche forming phase 1 of 3 to include house numbers 47-78 (Units 1-32) and 113-115 (Units 67-69)

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    CN0138917KE

    Construction of 6no. dwellings forming phase 2A of 3 to include house numbers 107-112 (Units 62-66)

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    CN0142929KE

    Construction of 24no. dwellings forming phase 2B of 3 to include house numbers 79-86 (Units 33-40) 91-106 (Units 45-60)

    24 units stated for this notice or phase; not a project total.

    · Notice evidence

  7. Notified commencement

    SN0014503KE

    Construction of 1block comprising 4no. dwellings (maisonettes) forming phase 2c of 3 to include house numbers 87-90 (Units 41-44)

    4 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.