Planning case 181109

Galway County Council · 181109 · Headford, Galway

Latest linked evidence

Notified commencement · 2021-08-03

CN0079132GC · Re-development of OPW Offices, Headford, Co. Galway: The development will consist of the demolition of 2 no. existing single/two storey office buildings located to the South of the site. The construction of a new two storey L-Shaped office block located on the site of the demolished buildings fronting onto St. Georges Sq. In addition, works will include alteration, upgrading and refurbishment of the existing rear office block located to the South-West of the site which will be connected to the new office building. External works will include hard and soft landscaping, new car-parking facilities and bicycle stands, new steps and ramps to moderate rising ground levels existing on site, new hard landscaping along the boundary with St. George’s Square, new gate and railings and reduced boundary wall to the laneway to the South, reoriented entrance gateway with signage on adjacent wall, replacement of boundary wall to the South-West with a retaining wall within the boundary, signage to front porch, new foul and surface drainage systems and all associated ancillary site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    181109

  2. Planning decision

    181109

    Conditional permission

  3. Grant date recorded

    181109

  4. Notified commencement

    CN0064574GC

    Phase 1 of 3 (Enabling / Mobilisation Works) - Demolition of Existing Hut & part of the Boundary wall, Re – Routing / Diversion of Existing Utilities, Construction of E.S.B. Substation, Forming 2 No. New Access Gates & installation of Temporary Accomodation Portacabins.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    CN0079132GC

    Re-development of OPW Offices, Headford, Co. Galway: The development will consist of the demolition of 2 no. existing single/two storey office buildings located to the South of the site. The construction of a new two storey L-Shaped office block located on the site of the demolished buildings fronting onto St. Georges Sq. In addition, works will include alteration, upgrading and refurbishment of the existing rear office block located to the South-West of the site which will be connected to the new office building. External works will include hard and soft landscaping, new car-parking facilities and bicycle stands, new steps and ramps to moderate rising ground levels existing on site, new hard landscaping along the boundary with St. George’s Square, new gate and railings and reduced boundary wall to the laneway to the South, reoriented entrance gateway with signage on adjacent wall, replacement of boundary wall to the South-West with a retaining wall within the boundary, signage to front porch, new foul and surface drainage systems and all associated ancillary site works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.