Planning case 17603

Clare County Council · 17603 · Ennistymon, Clare

Latest linked evidence

Notified commencement · 2021-06-01

The Demolition of the existing single storey Scoil Mhuire Post Primary School Buildings & the existing two storey Scoil Mhainchín Primary School Buildings; Construction of new 3-storey Post Primary School with connected Sports Hall, 2-storey Primary School, new internal road with set-down areas for buses and cars, ESB substation, switch room, ancillary store rooms, boiler house, car parking, ball courts, landscaping and associated site works;New site entrance from Lahinch Road and new boundary treatment;New vehicular traffic lane and associated road works at the junction of proposed site entrance and Lahinch Road

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    17603

  2. Planning decision

    17603

    Conditional permission

  3. Grant date recorded

    17603

  4. Notified commencement

    Commencement notice

    The Demolition of the existing single storey Scoil Mhuire Post Primary School Buildings & the existing two storey Scoil Mhainchín Primary School Buildings; Construction of new 3-storey Post Primary School with connected Sports Hall, 2-storey Primary School, new internal road with set-down areas for buses and cars, ESB substation, switch room, ancillary store rooms, boiler house, car parking, ball courts, landscaping and associated site works;New site entrance from Lahinch Road and new boundary treatment;New vehicular traffic lane and associated road works at the junction of proposed site entrance and Lahinch Road

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.