Planning case 212042

Meath County Council · 212042 · Ashbourne, Meath

Latest linked evidence

Notified commencement · 2023-03-17

Provision of the Sprinkler System Pumphouse serving Unit 12E, Ashbourne B.P., Co. Meath and associated works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    212042

  2. Planning decision

    212042

    Conditional permission

  3. Grant date recorded

    212042

  4. Notified commencement

    Commencement notice

    Construction of warehousing unit (Unit 12F) with ancillary office/staff facilities and all associated site development works, located at the site north-east of Ashbourne Business Park, Ashbourne, Co. Meath.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    Construction of warehousing unit (Unit 12E) with ancillary office/staff facilities and all associated site development works, located at the site north-east of Ashbourne Business Park, Ashbourne, Co. Meath.

    Quantity not established for this notice.

    · Notice evidence

  6. Notified commencement

    Commencement notice

    Construction of ESB sub-station serving warehousing Units 12E & 12F at the site located at the site north-east of Ashbourne Business Park, Ashbourne, Co. Meath - and all associated site development works.

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    Commencement notice

    Provision of the Sprinkler System Pumphouse serving Unit 12E, Ashbourne B.P., Co. Meath and associated works.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.