Kilkenny County Council · 21348 · Poulgour, Kilkenny City, Kilkenny
Latest linked evidence
Notified commencement · 2023-01-03
Phase 06 of a new Residential Development, at ‘Castle Oaks’, Poulgour, Kilkenny City, Co. Kilkenny. Phase 06 consists of the construction of 1 No. dwelling and a duplex building containing 2 No. dwellings, together with all associated site and ancillary works.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.
Source history
Timeline
Planning application received
21348
Planning decision
21348
Conditional permission
Grant date recorded
21348
Notified commencement
Commencement notice
Phase 01 of a new Residential Development, at Poulgour, Kilkenny City, Co. Kilkenny. Phase 01 consists of the construction of 17 No. Dwellings, forming the new internal access roadway, constructing the new foul water pumping station and storm water attenuation area, together with all associated site and ancillary works.
17 units stated for this notice or phase; not a project total.
Phase 02 of a new Residential Development, at ‘Castle Oaks’, Poulgour, Kilkenny City, Co. Kilkenny. Phase 02 consists of the construction of 10 No. Dwellings, together with all associated site and ancillary works.
10 units stated for this notice or phase; not a project total.
Phase 03 of a new Residential Development, at ‘Castle Oaks’, Poulgour, Kilkenny City, Co. Kilkenny. Phase 03 consists of the construction of 11 No. Dwellings, together with all associated site and ancillary works.
11 units stated for this notice or phase; not a project total.
Phase 05 of a new Residential Development, at ‘Castle Oaks’, Poulgour, Kilkenny City, Co. Kilkenny. Phase 05 consists of the construction of an apartment building containing 27 no. dwellings, together with all associated site and ancillary works.
Phase 04 of a new Residential Development, at ‘Castle Oaks’, Poulgour, Kilkenny City, Co. Kilkenny. Phase 04 consists of the construction of 7 No. Dwellings and a duplex building containing 2 No. Dwellings, together with all associated site and ancillary works.
9 units stated for this notice or phase; not a project total.
Phase 06 of a new Residential Development, at ‘Castle Oaks’, Poulgour, Kilkenny City, Co. Kilkenny. Phase 06 consists of the construction of 1 No. dwelling and a duplex building containing 2 No. dwellings, together with all associated site and ancillary works.
3 units stated for this notice or phase; not a project total.