Latest linked evidence
Notified commencement · 2024-09-24
The development will consist of (a) - Demolition and safe removal of existing chimney stack and roof hip structure at roof level to side (West Elevation). (b) - The raising of existing gable wall and 1no. window with obscure glass at side (West Elevation) with modification / extension of existing roof structure. (c) - Construction of 1no. dormer at rear, including the conversion of existing attic space for domestic storage / ancillary accommodation, incorporating new access stairs and shower room, with 3no. windows and 1no. velux roof-light at rear (North Elevation) and 2no. velux roof-lights at front (South Elevation). (d) - The widening of existing vehicular entrance from 2.5 meters to 4.2 meters with a new permeable finish to front driveway, including all necessary site works to facilitate the development.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.