Notified commencement · 2024-02-12
The development consists of: (i) the demolition of an existing stone clad wall with railing and the removal of 3 no. silver birch trees located adjacent to the Elm Mount Unit Building; (ii) the construction of a single storey over basement Electrical Energy Centre (c. 358.5 sqm) and external stone clad wall to the south-west of the St. Vincent’s University Hospital Campus to serve St. Vincent’s University Hospital; (iv) provision of a green roof to proposed Electrical Energy Centre, and; (v) all associated site development works and site services above and below ground required to facilitate the development.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.