Save this project to account
Connected planning records

Planning case FW15A0135

Fingal County Council · FW15A0135 · Blanchardstown, Dublin

Latest linked evidence

Notified commencement · 2016-03-02

SN0001042FL · Construction of a single storey c.76sq.m. building for use as a Water and Oil storage pump room.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    FW15A0135

    Official source

  2. Planning decision

    FW15A0135

    Permission granted

    Official source

  3. Grant date recorded

    FW15A0135

    Official source

  4. Notified commencement

    SN0000972FL

    Construction of a new two-storey c.15,938sq.m. building for use as Data Storage with electrical rooms for electronic operations, mechanical plant rooms and support areas including a loading bay, offices. welfare facilities and ancillary external installations.

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    SN0001022FL

    Construction of a Client Electrical Control Building as part of a Data Centre development as Granted by Final Order PF/0026/16 and Decision Order No. PB/0526/15

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

  6. Notified commencement

    SN0001041FL

    Construction of a single storey c.59sq.m. building for use as a Water storage pump room

    Quantity not established for this notice.

    · Notice evidence

  7. Notified commencement

    SN0001042FL

    Construction of a single storey c.76sq.m. building for use as a Water and Oil storage pump room.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.