Final grant issued 25 August 2026 for redevelopment as a 40-unit apart-hotel. Tourist accommodation, retained structure and selective reconstruction are distinct from a new residential supply scheme.
Final grant is for a 40-unit apart-hotel
Final permission for tourist accommodation in the existing Grand Hotel
What the evidence says
The final grant issued on 25 August covers redevelopment of the existing four-storey former hotel into 40 apart-hotel units with a stated gross floor area of 3,812 m². Condition 2 requires the premises to operate as apart-hotel or tourist accommodation and restricts a later change of use.
Why it may matter — interpretation
Hospitality fit-out and service suppliers should assess an apart-hotel refurbishment scope rather than assume forty conventional homes.
What is not established
Commencement, operating agreement, detailed room procurement and any later change-of-use approval are not established.
Inspect the evidence
Final grant for Grand Hotel redevelopment · p.1
Redevelopment of former hotel into 40-unit apart-hotel, 3812 m² · Issued 2026-08-25 · Final grant 25 August following decision 17 July · Checked 2026-09-07
Redevelopment of former hotel into 40-unit apart-hotel, 3812 m²
Final grant for Grand Hotel redevelopment · p.2
Final grant signed 25 August 2026 · Issued 2026-08-25 · Final grant 25 August following decision 17 July · Checked 2026-09-07
Final grant signed 25 August 2026
Decision notification and operative conditions · p.5
Condition 2: apart-hotel/tourist accommodation and change-of-use restriction · Issued 2026-07-17 · July decision conditions incorporated by final grant · Checked 2026-09-07
Condition 2: apart-hotel/tourist accommodation and change-of-use restriction
Sections separate retained walls from selective demolition and new work
Submitted P02.1 structural interfaces and demolition scope; not a structural certification
What the evidence says
The proposed section distinguishes retained walls, new blockwork and new internal studs. The demolition sections identify removal of corner extensions, selected internal stairs and roof structures, with part of the existing ground floor lowered by 820 mm. The scope therefore includes substantial interior stripping and local reconstruction around retained fabric.
Why it may matter — interpretation
Demolition, structural and interior teams need to coordinate temporary support, retained levels and new work before fixing refurbishment quantities.
What is not established
Structural survey results, temporary-works design, asbestos survey and construction sequencing are not established.
Inspect the evidence
Proposed section 05 · p.1
Section 05: retained walls, blockwork, internal studs and altered floor level · Issued 2026-05-15 · P23-303K-GHT-SW-XXX-DR-KDS-AR-3012 revision P02.1 · Checked 2026-09-07
Section 05: retained walls, blockwork, internal studs and altered floor level
Demolition sections 04 and 05 · p.1
Sections 04 and 05: selective demolition, roof reconstruction and 820 mm floor lowering · Issued February 2026 (month only) · P23-303K-GHT-SW-XXX-DR-KDS-AR-3021 revision P02.1; issue row has unspecified February day; received 25 May · Checked 2026-09-07
Sections 04 and 05: selective demolition, roof reconstruction and 820 mm floor lowering
Roof works combine membranes, a green roof and maintenance access
May planning roof proposal subject to the later finish condition
What the evidence says
The roof plan shows insulated membrane systems to flat roofs, a green roof above ground-floor structures, maintenance walkways, fall-arrest provision, AOVs and lift/service access. It proposes slate replacement to the pitched roof, but condition 3 requires the reconstructed pitched-roof finish on Broad Street and Hotel Square to be agreed before commencement.
Why it may matter — interpretation
Roofing and access specialists should coordinate the different roof zones and penetrations while retaining the council agreement on the visible pitched finish.
What is not established
Agreed pitched-roof finish, final waterproofing specification, fixing details, fall-arrest certification and installed plant are not established.
Inspect the evidence
Proposed roof plan · p.1
P02.1 roof plan: membranes, green roof, access and proposed slate replacement · Issued 2026-05-15 · P23-303K-GHT-SW-L04-DR-KDS-AR-1024 revision P02.1; received 25 May · Checked 2026-09-07
P02.1 roof plan: membranes, green roof, access and proposed slate replacement
Decision notification and operative conditions · p.5
Condition 3(d): pitched-roof finish to be agreed before commencement · Issued 2026-07-17 · July decision conditions incorporated by final grant · Checked 2026-09-07
Condition 3(d): pitched-roof finish to be agreed before commencement
The permission removes roof and projecting signage from the submitted proposal
Operative conditions modifying the submitted elevations
What the evidence says
Condition 3 omits roof-mounted illuminated signage on the Broad Street elevation and projecting signage on the specified rear elevation. Wall-mounted alternatives may be acceptable only with written agreement. Detailed signage specifications and external finish samples also require agreement before commencement.
Why it may matter — interpretation
Facade and signage suppliers need the agreed revisions rather than the original illuminated-sign proposal as their scope.
What is not established
Accepted replacement signs, finish samples, lighting details and installation are not established.
Inspect the evidence
Decision notification and operative conditions · p.5
Conditions 3 and 4: omitted signs, agreed alternatives and external finish samples · Issued 2026-07-17 · July decision conditions incorporated by final grant · Checked 2026-09-07
Conditions 3 and 4: omitted signs, agreed alternatives and external finish samples
The declared pages of these government-published PDFs were visually inspected. Other catalogue files, later compliance, procurement and installed specifications were not established. Historical weekly membership is retained separately from these document dates.