Notified commencement · 2023-01-16

The project consists of: (i) The refurbishment of an existing 5 no. storey building to provide for a new façade treatment to all elevations. (ii) The extension of the existing 5th storey set back level in line with the main façade along the northern elevation. (iii) The provision of 2 no. additional floors, set back from the north, east and west elevations. (iv) The provision of a café unit to the west side of the building fronting Georges Quay and Luke Street to the east at ground & mezzanine level (v) Amendments to the ground floor layout to provide for a new entrance lobby to the office to the east of the building. (vi) Amendments to basement level to provide for a reconfiguration of the car parking spaces, 80 no. cycle parking spaces, 3 no. motorbike spaces, new shower and locker rooms, staff amenities, bin store, managers office and plant room. The existing access to basement will remain unchanged. (vii) Alterations to the hard and soft landscaping, SUDs drainage provision of plant at basement and roof level, 2 no. terraces at 5th and 6th floor to the north, east and west, green roofs and all other associated site development works necessary to facilitate the development The proposed development is located on site of 0.14ha at Block B, Georges Quay, Dublin 2,. The site is bound by Georges Quay to the north, Georges Quay Plaza to the south, 1GQ to the east and Tara Street Station/Railway bridge to the west. Luke Street runs through the site in a north/south direction wit

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    253220

  2. Planning decision

    253220

    Permission granted

  3. Grant date recorded

    253220

  4. Notified commencement

    Commencement notice

    Enabling & demolition works including erection of hoarding, removal of façade & soft trip of building interior

    Quantity not established for this notice.

    · Notice evidence

  5. Notified commencement

    Commencement notice

    The project consists of: (i) The refurbishment of an existing 5 no. storey building to provide for a new façade treatment to all elevations. (ii) The extension of the existing 5th storey set back level in line with the main façade along the northern elevation. (iii) The provision of 2 no. additional floors, set back from the north, east and west elevations. (iv) The provision of a café unit to the west side of the building fronting Georges Quay and Luke Street to the east at ground & mezzanine level (v) Amendments to the ground floor layout to provide for a new entrance lobby to the office to the east of the building. (vi) Amendments to basement level to provide for a reconfiguration of the car parking spaces, 80 no. cycle parking spaces, 3 no. motorbike spaces, new shower and locker rooms, staff amenities, bin store, managers office and plant room. The existing access to basement will remain unchanged. (vii) Alterations to the hard and soft landscaping, SUDs drainage provision of plant at basement and roof level, 2 no. terraces at 5th and 6th floor to the north, east and west, green roofs and all other associated site development works necessary to facilitate the development The proposed development is located on site of 0.14ha at Block B, Georges Quay, Dublin 2, . The site is bound by Georges Quay to the north, Georges Quay Plaza to the south, 1GQ to the east and Tara Street Station/Railway bridge to the west. Luke Street runs through the site in a north/south direction wit

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.