Save this project to account
Connected planning records

Planning case 1850439

Donegal County Council · 1850439 · Laghey, Donegal

Latest linked evidence

Notified commencement · 2019-04-18

CN0050404DL · (1) REFURBISHMENT OF THE FORMER RECTORY BUILDING, (2) PROVISION OF A SINGLE STOREY EXTENSION TO THE FORMER RECTORY BUILDING TO PROVIDE FOR ADDITIONAL LIVING ACCOMMODATION , (3) THE EXTENSION AND REFURBISHMENT OF THE EXISTING REAR OUTBUILDINGS TO PROVIDE ADDITIONAL HABITABLE ACCOMMODATION ANCILLARY TO THE MAIN HOUSE, (4) DECOMMISSIO NING OF THE EXISTING SEPTIC TANK ON SITE AND PROVISION OF NEW EFFLUENT TREATMENT SYSTEM AND POLISHING FILTER, (5) WIDENING OF FRONT ENTRANCE AND ALL ASSOCIATED SITE WORKS. THE SUBJECT BUILDING IS A PROTECTED STRUCTURE REF NO. 40848001

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    1850439

  2. Planning decision

    1850439

    Conditional permission

  3. Grant date recorded

    1850439

  4. Notified commencement

    CN0050404DL

    (1) REFURBISHMENT OF THE FORMER RECTORY BUILDING, (2) PROVISION OF A SINGLE STOREY EXTENSION TO THE FORMER RECTORY BUILDING TO PROVIDE FOR ADDITIONAL LIVING ACCOMMODATION , (3) THE EXTENSION AND REFURBISHMENT OF THE EXISTING REAR OUTBUILDINGS TO PROVIDE ADDITIONAL HABITABLE ACCOMMODATION ANCILLARY TO THE MAIN HOUSE, (4) DECOMMISSIO NING OF THE EXISTING SEPTIC TANK ON SITE AND PROVISION OF NEW EFFLUENT TREATMENT SYSTEM AND POLISHING FILTER, (5) WIDENING OF FRONT ENTRANCE AND ALL ASSOCIATED SITE WORKS. THE SUBJECT BUILDING IS A PROTECTED STRUCTURE REF NO. 40848001

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.