Planning case SD21A0203

South Dublin County Council · SD21A0203 · Lucan, Dublin

Latest linked evidence

Notified commencement · 2022-02-15

Development of 2no. Data Buildings (DUB 14 & 15), Central Administration Building (CAB), Water Treatment Building and compound and Sprinkler Pump Room including campus development of bicycle shelters, car park layouts, site development works, including underground water and building services provision, landscaping, internal security and compound enclosure fencing, and associated works; the remainder of the development (including permitted temporary construction car parking) to be carried out in accordance with parent permission SD20A/0283 and revised planning permission SD21A/0203.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    SD21A0203

    Official source

  2. Planning decision

    SD21A0203

    Permission granted

    Official source

  3. Grant date recorded

    SD21A0203

    Official source

  4. Notified commencement

    Commencement notice

    Development of 2no. Data Buildings (DUB 14 & 15), Central Administration Building (CAB), Water Treatment Building and compound and Sprinkler Pump Room including campus development of bicycle shelters, car park layouts, site development works, including underground water and building services provision, landscaping, internal security and compound enclosure fencing, and associated works; the remainder of the development (including permitted temporary construction car parking) to be carried out in accordance with parent permission SD20A/0283 and revised planning permission SD21A/0203.

    Quantity not established for this notice.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.