Planning case 211533

Wicklow County Council · 211533 · Áth na Sceire, Wicklow

Latest linked evidence

Notified commencement · 2024-08-08

CN0118916WW · Construction of Phase 2 being 56 No. dwelling houses; 10 No. 5 Bed two storey detached; 8 No. 4 Bed two storey detached; 10 No. two storey 4 Bed semi-detached; 14 No. two storey 3 Bed semi-detached; 4 No. 2 Bed two storey semi-detached and 10 No. 2 Bed semi-detached bungalows; addresses as follows; 13 -22 The Wisteria; 1-13 The Iris; 1-16 The Orchid and 1-17 The Foxglove

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    211533

  2. Planning decision

    211533

    Conditional permission

  3. Grant date recorded

    211533

  4. Notified commencement

    CN0117082WW

    Construction of 28 No. dwelling houses; 6 no. two storey detached and 22 no. two storey semi-detached

    28 units stated for this notice or phase; not a project total.

    · Notice evidence

  5. Notified commencement

    CN0118916WW

    Construction of Phase 2 being 56 No. dwelling houses; 10 No. 5 Bed two storey detached; 8 No. 4 Bed two storey detached; 10 No. two storey 4 Bed semi-detached; 14 No. two storey 3 Bed semi-detached; 4 No. 2 Bed two storey semi-detached and 10 No. 2 Bed semi-detached bungalows; addresses as follows; 13 -22 The Wisteria; 1-13 The Iris; 1-16 The Orchid and 1-17 The Foxglove

    56 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.