Notified commencement · 2017-04-10

Permission for demolition of single storey rear element, front porch and side chimney to existing 2 storey semi-detached dwelling. Construction of a two storey extension to side and rear (110 sqm) (part single storey to rear) and new single storey porch to front of existing dwelling, all with external insulation, render finish and the addition of roof lights. Also, permission is sought to increase the width of site entrance to 3.5m, new pier, dished kerb and all associated internal and site works.

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Source history

Timeline

  1. Planning application received

    D16A0620

  2. Planning decision

    D16A0620

    Permission granted

  3. Grant date recorded

    D16A0620

  4. Notified commencement

    Commencement notice

    Permission for demolition of single storey rear element, front porch and side chimney to existing 2 storey semi-detached dwelling. Construction of a two storey extension to side and rear (110 sqm) (part single storey to rear) and new single storey porch to front of existing dwelling, all with external insulation, render finish and the addition of roof lights. Also, permission is sought to increase the width of site entrance to 3.5m, new pier, dished kerb and all associated internal and site works.

    1 units stated for this notice or phase; not a project total.

    · Notice evidence

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.