Notified commencement · 2020-08-10
Site Enabling Works and Sports Pitch Formation Enabling works package to involve the demolition of the existing boundary wall, followed by the construction of the new entrance and reconstruction of the boundary wall as per the planning details. Following this, the formation of the sports pitch levels shall be commenced, including stripping of topsoil, levelling of pitch platforms and seeding of pitches. Internal haul roads and laydown areas for plant and materials shall also be formed. Latter phases (phases 2 and 3) of development will include the pitch floodlighting, clubhouse and changing room construction. This enabling works phase will include earthworks type activities only (i.e. no construction of buildings). These latter phases shall be commenced at a later stage under separate commencement notices.
This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.